PROJECT MILESTONE

Project Milestone Schedule
Milestone From Appointment Date Contractual Dates as per CA Target/Ach. Dates Milestone Event
MS-1 150 days 09-02-2023 20% of the Physical & Financial Progress.
MS-2 330 days 08-08-2023 35% of the Physical & Financial Progress.
MS-3 510 days 04-02-2024 75% of the Physical & Financial Progress.
Schedule Completion Days 730 days 11-09-2024 Shall have completed the Project in accordance with this Agreement.